National Green Tribunal (NGT), Principal Bench, New Delhi: The Bench of Justice Adarsh Kumar Goel (Chairperson) and Justice Sheo Kumar Singh (Judicial Member) and Dr Nagin Nanda (Expert Member)declined any relief to the applicant seeking an injunction against the demolition of Dhobi Ghat.

The instant application sought an injunction against the demolition of Dhobi Ghat, Okhla Delhi.

Applicant on an earlier occasion had approached the Delhi High Court by way of WP (C) 8963 of 2020, Muslim Kassar Vikas Sangthan (Reg.) v. Delhi Development Authority, the said petition was disposed of on 12-11-2020, wherein the Court had asked the petitioners to approach the NGT. 

Tribunal found the grievance to be out of the ambit of Sections 14 and 15 of the National Green Tribunal Act, 2010.

Bench added that jurisdiction of NGT under Sections 14 and 15 can be invoked by a victim of pollution for the restoration of environment or for compensation to the victim, and the said issue is not shown in the instant matter.

Hence, in view of the above application was disposed of. [Muslim Kassar Vikas Sangthan (Regd.) v. Delhi Development Authority, 2020 SCC OnLine NGT 867, decided on 11-12-2020]


Also Read:

Section 14 of the NGT Act:

Tribunal to settle disputes.—(1) The Tribunal shall have the jurisdiction over all civil cases where a substantial question relating to environment (including enforcement of any legal right relating to environment), is involved and such question arises out of the implementation of the enactments specified in Schedule I.

(2) The Tribunal shall hear the disputes arising from the questions referred to in sub-section (1) and settle such disputes and pass order thereon.

(3) No application for adjudication of dispute under this section shall be entertained by the Tribunal unless it is made within a period of six months from the date on which the cause of action for such dispute first arose:

Provided that the Tribunal may, if it is satisfied that the applicant was prevented by sufficient cause from filing the application within the said period, allow it to be filed within a further period not exceeding sixty days.

Section 15 of the NGT Act:

Reliefcompensation and restitution.—(1) The Tribunal may, by an order, provide,—

(arelief and compensation to the victims of pollution and other environmental damage arising under the enactments specified in the Schedule I (including accident occurring while handling any hazardous substance);

(b) for restitution of property damaged;

(c) for restitution of the environment for such area or areas,

as the Tribunal may think fit.

(2) The relief and compensation and restitution of property and environment referred to in clauses (a), (band (c) of sub-section (1) shall be in addition to the relief paid or payable under the Public Liability Insurance Act, 1991 (6 of 1991).

(3) No application for grant of any compensation or relief or restitution of property or environment under this section shall be entertained by the Tribunal unless it is made within a period of five years from the date on which the cause for such compensation or relief first arose:

Provided that the Tribunal may, if it is satisfied that the applicant was prevented by sufficient cause from filing the application within the said period, allow it to be filed within a further period not exceeding sixty days.

(4) The Tribunal may, having regard to the damage to public health, property and environment, divide the compensation or relief payable under separate heads specified in Schedule II so as to provide compensation or relief to the claimants and for restitution of the damaged property or environment, as it may think fit.

(5) Every claimant of the compensation or relief under this Act shall intimate to the Tribunal about the application filed to, or, as the case may be, compensation or relief received from, any other court or authority.